Overall Project Review Messages

Review Date Review Message Review Added By Review Attended By
01 Nov 2012 The SE informed that the additional proposal of laying 400mm raw water pumping main was sanctioned and tendered but no response. Works as per original proposal has been completed. The scheme will be commissioned only after completion of additional proposal. Power Connection is yet to be obtained. Pumpset and Transformer are erected. Managing Director ,Superintending Engineer/ Executive Engineer