Projects

  
Search ongoing projects Example: ‘project code’ or ’project name’ or ’location’

Main Office New Building - ELV Works

Project Main Office New Building - ELV Works
Project Code PLAN0523124
Work Category Building
Funding Agency PLAN
Client Department
Description Main Office New Building - ELV Works
Status On-going
District Ernakulam
Executing Office KMC HO
AS Amount (Rs) 33790598
AS Number 06
TS Amount (Rs)
TS Number
Actual Project Completion Date Date is not specified
Coverage

Packages

No. Project Name Location View
No Packages has been added for this project.

No status have been added to this project

No project review have been added to this project

Duration & Sanction dates

Date of start of Project Date is not specified
Scheduled date of Completion of the Project 13 Mar 2024
Expected date of Completion 18/12/2024

Processing Dates

AS Date 22 May 2023

Other details

Project Officers View